Project Name : YEKA-4 SOLAR POWER PLANT PROJECT
Project/Contract Title and Brief Description of Work : KES JV OHTL PROJECT PROCUREMENT, CONSTRUCTION, TEST AND COMMISSIONING WORKS
Work Location Country : Turkey
Work Location City : Niğde
Voltage (kV) : 154
Conductors : 1272 MCM Phesant
Lenght (km) : 56
Tower Quantity : 185
Signing Date : 01.01.2023
Date of Provisional Acceptance : 15.11.2023
Client : Ecogreen-Smart-Kalyon