Project Name : YAHYALI WIND TURBINE POWER PLANT PROJECT
Project/Contract Title and Brief Description of Work : SCADA RTU SYSTEM (73 SUBSTATION)
Work Location Country : Türkiye
Work Location City : Kayseri
Voltage (kV) : 154/34.5
Bay Quantity : -
Total Transformer Capacity (MVA) : 100
Signing Date : 31.05.2016
Date of Provisional Acceptance : 28.10.2016
Client : 4A Elektrik Elektronik Teknoloji San. A.Ş.