Project Name : FIRST STAGE OF INCREASING THE RELIABILITY OF POWER SUPPLY TO THE CITY OF ASHGABAT
Project/Contract Title and Brief Description of Work : KÖŞGİ 35/10 Kv S/S ORBİTA 110/35/10 Kv S/S 2 PC. TP INSTALLATION
Work Location Country : Turkmenistan
Work Location City : Ashgabat
Voltage (kV) :
10/0.4
35/10/0.4
110/35/10
Bay Quantity : 8
Total Transformer Capacity (MVA) : 80
Signing Date : 20.11.2014
Date of Provisional Acceptance : 23.02.2016
Client : Çalık Energy